Wellington City Council to ask for public input on 5-year Capital Improvement project plan
by Tracy McCue, Sumner Newscow — So what is the future of Wellington? What projects would you like to see the city complete with your tax money.
The Wellington City Council is encouraging all city taxpayers to attend a public information meeting/council work session on Thursday, June 13 at 6 p.m. at the Memorial Auditorium in Wellington.
The purpose of the public information meeting/council work session is to discuss the proposed 2014-2019 Capital Improvement Plan and various projects/issues.
So what exactly is a Capital Improvement Plan? Think of it as a city to-do list.
Every half decade, the council puts together a list of projects which need to be done in the next five years.
Wellington City Manager Gus Collins said the objective is to analyze projects that would be needed and to start the process of providing funding for the prioritized projects so that there is no shocking developments moving forward.
Collins gave the examples of the Lincoln Street Improvement project and the Vandenburgh Improvement project as two projects that were included in the previous year CIPs.
He said 90 projects were submitted to the City Manager’s office by department heads and were then sent to the Planning Commission to rate and review.
Collins said the Planning Commission ratings were then passed on to the council to review. He said the reason for this meeting is to see what the public thinks.
“This list in no way set in stone,” Collins said. “We will adopt it in the middle of August along with the annual budget, but it will be up for review annually.”
The master list which has already been reviewed by the Wellington Planning Commission is listed below. Collins encourages the public to review the list and see if there is a project not listed or one that is not prioritized high enough.
|
City of Wellington CAPITAL IMPROVEMENT Requests for Budget Year 2014 to 2019 |
|||||
|
Dept Name |
Category |
Project Title / Item / brief details |
additional details |
Cost |
Cap Imp Yr |
|
Admin |
Admin |
Memorial Auditorium renovation – HVAC |
$350,000 |
2014 |
|
|
Airport |
Airport |
Runway extension design |
FAA 90%=90k, City 10%=10k. Oil lease revenue |
$100,000 |
2014 |
|
Airport |
Airport |
Runway extension construction & lagoon relocation |
FAA 90%, City 10%. Oil lease revenue & other private/public funding |
$1,860,106 |
2015 |
|
Airport |
Airport |
Replace asphalt portion of Apron |
FAA=991,558, City=110,173. General fund, airport revenue ??? |
$1,101,731 |
2016 |
|
Airport |
Airport |
T-hanger taxi lanes recontruction |
FAA=519,001, City=57,667. General fund, airport revenue ??? |
$576,669 |
2017 |
|
Airport |
Airport |
Runway extension #2 |
FAA=1,446,877, City=160,764. General fund, airport revenue ??? |
$1,607,641 |
2018 |
|
Economic Dev |
Admin |
Engineering study- new Industrial Park East US160 corridor |
$50,000 |
2014 |
|
|
Economic Dev |
Admin |
Hargis Creek Pedestrian & Bike Path |
Construction 433,558 80/20 w/KDOT. Construction engineering & contingency 108,388 80/20 w/KDOT. Design engineering 58,054 City. |
$600,000 |
2014 |
|
Elec Dist |
Utilities |
Automated Metering Infrastructure – Stage Three |
$214,000 |
2014 |
|
|
Elec Dist |
Utilities |
Breaker replacement – annual |
Annual amount |
$80,000 |
2014 |
|
Elec Dist |
Utilities |
Conductor Pulling System |
Used system |
$150,000 |
2014 |
|
Elec Dist |
Utilities |
Line upgrade & construction – annual |
Annual amount |
$100,000 |
2014 |
|
Elec Dist |
Utilities |
Short Term Improvements – Phase One DESIGN |
Design cost 2013/2014 |
$40,000 |
2014 |
|
Elec Dist |
Utilities |
Short Term Improvements – Phase One CONSTRUCTION |
Delayed from 2012. |
$4,290,000 Bond Issue |
2014 |
|
Elec Dist |
Utilities |
Automated Metering Infrastructure – Stage Four |
$85,000 |
2015 |
|
|
Elec Dist |
Utilities |
Digger Derrick Truck |
$200,000 |
2016 |
|
|
Elec Dist |
Utilities |
Feeder Circuit Protective Relays |
$80,000 |
2016 |
|
|
Elec Dist |
Utilities |
Overhead to Underground Substation Improvement |
$180,000 |
2016 |
|
|
Elec Dist |
Utilities |
Long Term Improvements – Stage One |
$2,282,500 |
2017 |
|
|
Elec Dist |
Utilities |
Overhead to Underground Conversion |
Annual amount – beginning 2017 |
$150,000 |
2017 |
|
Elec Dist |
Utilities |
Overhead to Underground Eastern Corridor |
$250,000 |
2017 |
|
|
Elec Dist |
Utilities |
Directional Boring Machine replacement |
$140,000 |
2018 |
|
|
Elec Prod |
Utilities |
Motor Control Center for Cooling Tower |
$50,000 |
2014 |
|
|
Elec Prod |
Utilities |
Fire System Controls Upgrade for Gas Turbine Generator |
$100,000 |
2015 |
|
|
Elec Prod |
Utilities |
Stack Replacement for Gas Turbine Generator |
$100,000 |
2015 |
|
|
Elec Prod |
Utilities |
Boiler Chemically Cleaned |
$60,000 |
2016 |
|
|
Elec Prod |
Utilities |
Condenser Tubes Inspected |
$60,000 |
2017 |
|
|
Elec Prod |
Utilities |
Fogging/Overspray System for Gas Turbine Generator |
$300,000 |
2018 |
|
|
Elec Prod |
Utilities |
Voltage Regulator for Steam Plant |
$250,000 |
2019 |
|
|
Engineering |
Streets |
Intersection Safety Funding project-16th & Woodlawn |
90% KDOT max of 500k, 10% City, City design 50k, plus easements & right of way |
$600,000 |
2014 |
|
Engineering |
Streets |
Intersection Safety Funding project-8th & G |
90% KDOT max of 300k, 10% City, City design cost 25k |
$325,000 |
2014 |
|
Dept Name |
Category |
Project Title / Item / brief details |
additional details |
Cost |
Cap Imp Yr |
|
Engineering |
Streets |
KLINK FY2014. North A street mill & overlay |
75%KDOT, 25%City. City design, utility adjustments & 25% construction = Total City 85k |
$266,576 |
2014 |
|
Engineering |
Public Works |
Structure demolition – annual |
Annual Amount |
$40,000 |
2014 |
|
Engineering |
Streets |
GeoKLINK FY2015-15th & Washington Intersection |
City share estimate 250k |
$725,500 |
2015 |
|
Engineering |
Streets |
Hillside, H street to 1/2 mile west (reconstruct gravel road) |
$100,000 |
2016 |
|
|
Fire |
Public Safety |
Tender, 2500 gal – replacing 1500 gal Tender |
Lease purchase or Grant |
$200,000 |
2014 |
|
Fire |
Public Safety |
Replace 1997 Luverne Engine |
Lease purchase |
$475,000 |
2015 |
|
Fire |
Public Safety |
Self contained breathing apparatus |
$170,000 |
2017 |
|
|
PW- Cemetery |
Public Works |
Backhoe for Cemetery & Street use |
structure Lease Purchase |
$110,000 |
2014 |
|
PW- Cemetery |
Public Works |
Scattering Garden – Phase 1 |
Design 5k, Gazebo 20k, Landscaping 10k, Sidewalks/Parking 15k |
$50,000 |
2014 |
|
PW- Cemetery |
Public Works |
Scattering Garden – Phase 2 |
Landscaping 12k, Reflection pond/site furnishings 25k, Sidewalks 8k |
$45,000 |
2016 |
|
PW- Cemetery |
Public Works |
Office/shop building |
Metal bldg 50k, concrete 18k, Materials 10k, Elec/plumbing/HVAC 22k |
$100,000 |
2017 |
|
PW- Cemetery |
Public Works |
Scattering Garden – Phase 3 |
Design 5k, Columbariums 25k, Landscaping 12k, Sidewalks 8k |
$50,000 |
2018 |
|
PW-Lake |
Public Works |
Heated fishing dock |
$80,000 |
2014 |
|
|
PW-Lake |
Public Works |
Rip rap rock for shore line – annual |
Annual amount. Possible grant funds. |
$30,000 |
2014 |
|
PW-Lake |
Public Works |
New campground – east side |
Electric hook-ups 25k, Rock pads 12k, Water 8k, Picnic tables/Fire rings 15k |
$60,000 |
2015 |
|
PW-Lake |
Public Works |
Beach restroom – prefabricated |
$80,000 |
2016 |
|
|
PW-Lake |
Public Works |
Rental pavillion |
$60,000 |
2017 |
|
|
PW-Lake |
Public Works |
Storm shelter – east side |
Possible grant KDWP |
$60,000 |
2018 |
|
PW-Lake |
Public Works |
Multiple boat slip/Fishing dock |
$80,000 |
2019 |
|
|
PW-Parks |
Public Works |
Light poles replacement-Sellers Park |
$80,000 |
2014 |
|
|
PW-Parks |
Public Works |
Rubber multi-purpose floor for Armory |
$50,000 |
2014 |
|
|
PW-Parks |
Public Works |
Sellers Park rental pavillion |
Design 5k, Metal bldg 70k |
$75,000 |
2014 |
|
PW-Parks |
Public Works |
Water slide replacement reserve |
Annual amount to build reserve. Estimated replacement cost 150k to 200k |
$20,000 |
2014 |
|
PW-Parks |
Public Works |
Worden Park Field #4 Phase 1. Construct backstop & install infield. |
$25,000 |
2014 |
|
|
PW-Parks |
Public Works |
Worden Park road & parking lot construction |
Will be combined with 25k approved in 2013 budget to begin project in 2014. |
$25,000 |
2014 |
|
PW-Parks |
Public Works |
2 10-row elevated bleachers for Hibbs-Hooten Field |
$35,000 |
2015 |
|
|
PW-Parks |
Public Works |
Metal building 40 x 60 |
Consolidate storage |
$30,000 |
2015 |
|
PW-Parks |
Public Works |
Worden Park Field #4 Phase 2. Construct dugouts & fencing. Prking areas |
Dugouts & fencing 25k, Road & parking lot 25k |
$50,000 |
2015 |
|
PW-Parks |
Public Works |
Hargis west restroom |
$25,000 |
2016 |
|
|
PW-Parks |
Public Works |
Jefferson Park restroom |
$30,000 |
2016 |
|
|
PW-Parks |
Public Works |
Land acquistion – Future park in eastern corridor area |
$45,000 |
2016 |
|
|
PW-Parks |
Public Works |
Woods Park bridge replacement |
North end of Donut Bay |
$50,000 |
2016 |
Page 2 of 3
|
Dept Name |
Category |
Project Title / Item / brief details |
additional details |
Cost |
Cap Imp Yr |
|
PW-Parks |
Public Works |
Worden Park Field #4 Phase 3 (Field lighting) |
$80,000 |
2016 |
|
|
PW-Parks |
Public Works |
Madison playground improvements |
$25,000 |
2017 |
|
|
PW-Parks |
Public Works |
Worden Park parking lot, road improvements |
$50,000 |
2017 |
|
|
PW-Parks |
Public Works |
McKinley playground improvements |
$25,000 |
2018 |
|
|
PW-Parks |
Public Works |
Restroom/Concession Hibbs-Hooten Field |
Deisgn 5k, Bldg 95k |
$100,000 |
2019 |
|
PW- Sanitation |
Public Works |
Automated Refuse Collection truck & containers |
Truck 215k, containers 155k |
$370,000 |
2014 |
|
PW- Sanitation |
Public Works |
Automated Curbside Recycling Collection truck & containers |
Truck 215k, containers 175k |
$390,000 |
2015 |
|
PW- Sanitation |
Public Works |
Replace landfill dozer |
$200,000 |
2016 |
|
|
PW-Streets |
Streets |
ADA complliance – annual |
Annual amount |
$25,000 |
2014 |
|
PW-Streets |
Streets |
Curb replacement program – annual |
Annual amount |
$50,000 |
2014 |
|
PW-Streets |
Streets |
Public Works Building modifications – annual for 2 yrs. |
Annual amount for 2014 and 2015 |
$50,000 |
2014 |
|
PW-Streets |
Streets |
Rubber Tire Loader lease |
Annual thru 2019 |
$13,000 |
2014 |
|
PW-Streets |
Streets |
Sidewalk replacement program – annual |
Annual amount |
$10,000 |
2014 |
|
PW-Streets |
Streets |
Tandem axle dump truck w/dump bed & snow plow (replace 1993 Ford tandem) |
Truck 85k, dump body 26k, snow plow 5k |
$116,000 |
2014 |
|
PW-Streets |
Streets |
Rubber tire loader (replacing smaller loader-1999 Komatsu) |
$180,000 |
2015 |
|
|
Wastewater |
Utilities |
Sewer system rehabillitation program – annual |
Annual amount |
$100,000 |
2014 |
|
Wastewater |
Utilities |
Worden Park sewer line |
Delayed from 2013 |
$200,250 |
2014 |
|
Wastewater |
Utilities |
Airport sewer line |
2 lagoon system at Airport would be eliminated. Line would also serve proposed Humane Society animal shelter |
$850,000 |
2017 |
|
Water Dist |
Utilities |
Bulk water filling station |
Station 35k, concrete slab 1k, Stand pipe 1k |
$37,000 |
2014 |
|
Water Dist |
Utilities |
Waterline Rehabilitation program – annual |
Annual amount |
$150,000 |
2014 |
|
Water Dist |
Utilities |
Crestview Rd/16th Street/H Street waterlines |
Delayed from 2013. Cost updated 2/15/2012 |
$574,625 Bond issue |
2015 |
|
Water Dist |
Utilities |
Single axle dump truck (replacing 1986 GMC) |
1986 GMC could be transferred to Golf |
$100,000 |
2015 |
|
Water Dist |
Utilities |
Backhoe |
$125,000 |
2016 |
|
|
Water Prod |
Utilities |
Pump rehabiliation – annual |
Annual amount |
$30,000 |
2014 |
|
Water Prod |
Utilities |
Variable Speed Drive Units |
$47,000 |
2014 |
|
|
Water Prod |
Utilities |
Clearwell cleaning |
$30,000 |
2016 |
|
|
Water Prod |
Utilities |
Water well field expansion |
drill 2 to 4 wells |
$1,400,000 |
2017 |
|
Water Prod |
Utilities |
Water Plant engineering study |
$31,000 |
2018 |